Morocco's electricity market is changing. For companies considering photovoltaic investments, the decisions announced by the National Electricity Regulatory Authority (ANRE) in February 2026 establish important benchmarks. They also raise a practical question: what is electricity generated by an industrial solar system actually worth?

The answer depends on how and when a site uses electricity, the regulations that apply and its grid-connection conditions. High generation alone does not guarantee the best economic return.

What about industrial battery storage (BESS)?

Surplus electricity remuneration rules alone do not establish whether an industrial battery investment makes economic sense. A feasibility assessment should examine the site's hourly demand, practical use cases, electrical constraints, real costs and applicable regulations. Our industrial energy storage (BESS) feasibility approach in Morocco explains those initial questions without assuming that storage is financially viable.

The new surplus electricity tariff

On 19 February 2026, ANRE announced tariffs for eligible surplus electricity during the period 1 March 2026 to 28 February 2027:

  • MAD 0.21/kWh during peak hours.
  • MAD 0.18/kWh during off-peak hours.

These figures apply within the relevant legal framework, including renewable electricity generation and self-production rules. They do not mean that every solar installation can automatically sell excess electricity. Eligibility, connection and export conditions must be verified for each project.

According to ANRE, the remuneration framework covers high- and extra-high-voltage networks and medium-voltage distribution networks. Low-voltage arrangements depend on the applicable technical and regulatory framework.

Official source: ANRE announcement on surplus electricity remuneration, 19 February 2026.

Why more production does not always mean greater savings

Consider a factory operating mainly during daylight hours. Much of its solar output may be used directly, reducing electricity purchased at the site's applicable tariff.

A company consuming most electricity at night faces a different situation. With the same PV capacity, the alignment between generation and demand may be weaker, increasing potential surplus. Any export value must be assessed against the applicable rules.

A self-consumed kilowatt-hour does not necessarily have the same economic value as a kilowatt-hour exported to the grid. Load profiles are therefore fundamental to system sizing.

An illustrative financial calculation

Suppose a project generates 100,000 kWh per year. Of this, 80,000 kWh are used on site and 20,000 kWh are surplus.

For illustration only, assume self-consumption avoids MAD 1.20/kWh and all surplus qualifies for an average MAD 0.18/kWh remuneration.

Item Calculation Illustrative gross value
Self-consumption 80,000 × MAD 1.20 MAD 96,000
Eligible surplus 20,000 × MAD 0.18 MAD 3,600
Total MAD 99,600

This is neither a commercial offer nor net profit. Avoided tariffs, export eligibility, hourly patterns, system losses, connection fees, maintenance, finance and taxes can all change the outcome. A sound feasibility study uses measured site data and documented assumptions.

Network tariffs: TURT, TURD and TSS

ANRE also announced the following regulated charges effective 1 March 2026:

Regulated component Tariff
TURT: national transmission network use 6.85 centimes/kWh
TURD: medium-voltage distribution network use 6.07 centimes/kWh
TSS: system services remuneration 6.81 centimes/kWh

These are distinct regulatory components, not amounts to add automatically to determine a customer's electricity bill. Applicability depends on the relevant transaction, rules and contracts.

Official source: ANRE network tariff announcement, 19 February 2026.

Five checks before investing in industrial solar

1. Understand when electricity is consumed. Annual totals are insufficient. Examine working days, weekends, seasons, evenings and peaks.

2. Estimate actual self-consumption. Size the system for measured demand and realistic changes in site operations.

3. Verify grid connection conditions. Export permission and possible remuneration must be confirmed for the specific project.

4. Assess storage separately. A battery may shift consumption or support critical loads, but its financial value and backup capability must be demonstrated.

5. Compare financial scenarios. Account for capital cost, maintenance, performance, financing, achievable savings and operating risks over the system's lifetime.

What this means for Moroccan businesses

Factories, logistics sites and farms should not choose PV capacity based solely on available roof area or equipment prices. A credible study starts with the site's operations and connects measured demand to expected solar generation, grid constraints and relevant regulation.

At Helio Core Technologies, we begin by examining energy use and operational requirements before evaluating a suitable technical solution.

Conclusion

ANRE's 2026 decisions are significant for Morocco's electricity sector. For investors, the key lesson is straightforward: a larger solar installation is not automatically a more profitable one.

The better question is not simply how much electricity can be generated, but when it will be used, for what purpose and under which conditions it creates value.

To discuss an assessment for your business, contact Helio Core Technologies.